Permit tracker

Bygglov · startbesked · strandskydd · avlopp — case numbers, status, conditions. Synced from permits.yaml in the vault.

Heads up The avlopp permit's 2-year start-work clause is a tolkningsfråga — Robin's read (15 May) is that installing before 25 Nov 2026 with unchanged placement may need no renewal. Placement was confirmed on site 25 May; a new installation quote is pending.

Avlopp (sewage) permit

lapsed Värmdö kommun — Bygg och Miljö

Original 2021 permit lapsed under the 2-year start-work rule. SUPERSEDED by Moderna Avlopp Offer 5832 (2026-06-22, approved by Brett): the turn-key price now includes myndighetskontakter — a FRESH tillståndsansökan + projektering — so Moderna files a new avlopp application rather than relying on the old permit, retiring the tolkningsfråga about MEA.2021.4441's survival. Placement per situationsplan confirmed 2026-05-25 (surveyor utsättning, approved by Tullicon). System: Ecobox Small minireningsverk, 5 PE / 750 L/day, Polynite phosphorus trap 500 kg, diffuse discharge to a gravel bed. Next step: BankID- sign Offer 5832 (tick fullmakt) before 2026-07-22, then Moderna submits the new ansökan to Värmdö kommun.

Case MEA.2021.4441 Ref BMH 6015 Granted 2021-11-25
Conditions (5)
  • Maximum 4-litre toilet flush; water-saving fixtures
  • Professional installation; annual service by an approved technician
  • Annual owner self-inspection; phosphorus filter replaced when pH drops below 9
  • Annual sludge removal
  • Nearest surface water: Långträsk (~55 m); drinking-water well ~50 m away

Slutbesked (final approval)

pending Värmdö kommun

Required before the buildings may be occupied. Submit on completion: confirmation that bygglov conditions were followed; facade photographs (all sides); chimney-sweep inspection protocol (fireplace, flue, roof safety); proof of approved sewage connection; any deviation approvals from the case officer.

Bygglov — Phase 2 (ändring av befintlig byggnad)

pending Värmdö kommun

Required for the Phase 2 renovation — enclosing the altan changes the fasad. A new ärende, separate from BYGG.2025.1705 (Phase 1 komplementbyggnader). Robert Sandell to lodge. Open question first: does enclosing the altan add BYA (and so re-open strandskydd)? No NEW strandskyddsdispens expected — same footprint, established hemfridszon — but confirm with Värmdö + Robert in writing before lodging, given the Dec 2024 new-build overturn.

Conditions (2)
  • Confirm in writing that no new strandskyddsdispens is required (same footprint)
  • Clarify whether enclosing the altan increases BYA

Anmälan — Phase 2 (load-bearing changes)

pending Värmdö kommun

Separate track from bygglov, required for the structural work — removing/ relocating load-bearing timmer walls and inserting beams. Triggers a kontrollplan. A structural engineer must size the beams (liggande timmer is monolithic — not a stud-wall job). KA engagement to be confirmed or a new uppdragsavtal signed.

KA Robert Sandell (RISE C000334) — confirm Phase 2 engagement

Startbesked

issued Värmdö kommun

Issued — construction may legally proceed. Simplified kontrollplan for komplementbyggnader (enkla ärenden) confirmed in the startbesked.

Case BYGG.2025.1705 Granted 2025-05-27

Strandskydd (shoreline protection) dispensation

granted Länsstyrelsen (County Administrative Board)

The property is inside the 100 m shoreline-protection zone. The 2022 application (Docs/KOMMUN/Bygglov/BygglovLKomp01.pdf) ticked "Helt ny byggnad alt. brygga", "Arbete i vatten", and "Trädfällning" — so the brygga was explicitly in scope alongside the new buildings. Dispens granted 2024-04-04. Decision document not saved locally — retrieve from Länsstyrelsen/Värmdö. Justification: area already built upon, access restricted from outside.

Granted 2024-04-04

Bygglov (building permit)

approved Värmdö kommun

Approved: studio/gäststuga 35 m² BYA/BTA + 94 m² deck; bastu 11.3 m² BYA/BTA, 1 m roof overhang; fireplaces in both. Classified as komplementbyggnader — may NOT be used as independent dwellings.

Case BYGG.2025.1705 Granted 2025-05-06 Applicant Josefine Adner Richards KA Robert Sandell (RISE cert C000334, valid to 2029-01-11)
Must start by May 2027 (2 yrs from legal force)Must complete by May 2030 (5 yrs from legal force)
Conditions (6)
  • Buildings may not be occupied until slutbesked (final approval) is issued
  • Studio must be connected to approved sewage before occupancy
  • LOD (local stormwater management) required; separate WC and BDT sewage lines recommended
  • Water-saving fixtures required
  • Staking-out and position verification required
  • Any deviation from the permit must be approved by the case officer before execution

The decision PDFs are under "Permit decisions" on the Documents page. Filled-in ansökan blanketter (personnummer) live in the vault's Docs/KOMMUN/ and are never published here.